June 6 update

Post by DaveLathrop57 on Fri Jun 06, 2014 7:03 pm

Progress is slow but plugging along on preparing 110 for the removal of the boiler from the frame.

17 - the decision has been made to replace the tubes now and run until she dies on the calendar in 2015. We anticipate safe-ending the tubes and rolling them back in after the 2015 15 year mandated inspection. So, we are buying our next set of tubes prematurely while obtaining the benefit of maintaining steam operation.

Tubes should go in this week, and next weekend (June 14-15) is reassembly of the front end and whatever else was to9rn down to facilitate the tube replacement. All are welcome, of course......and we should see 17 in service again for the July operating schedule.

Dave

DaveLathrop57

Posts : 242
Join date : 2013-04-14
Location : North Carolina, USA

View user profile

Back to top Go down

Re: June 6 update

Post by DaveLathrop57 on Thu Jun 12, 2014 10:27 pm

Tubes arrived today for 17, workdays planned every Saturday remaining in June to get 17 ready to run by July 11. Any interested person welcome to come by and lend a hand.

Dave

DaveLathrop57

Posts : 242
Join date : 2013-04-14
Location : North Carolina, USA

View user profile

Back to top Go down

Re: June 6 update

Post by DaveLathrop57 on Thu Jun 19, 2014 9:16 pm

June 19.....tubes in, hydro test done and all well. Fire up on July 11 for operating on July 12. All welcome as always.

Dave

DaveLathrop57

Posts : 242
Join date : 2013-04-14
Location : North Carolina, USA

View user profile

Back to top Go down

Re: June 6 update

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum